Construction History

  • Construction: Start 01 Dec 2002
  • Complete: Partially Nov. 2005
  • Finally May 2006

……………………………………….

  • Architect-Design -Mr. Emil Ksayer
  • Architect-Supervising -Osei-Kufour, Sohne, & Partners
  • Quantity Surveyor -Dodo Consult
  • Consultant-Structural -Grid Consult
  • Structural Engineer -Eng. Ismat Oueidea
  • Project Manager -Mr. Salah Kalmoni
  • General Contractor (Civil) -DeSimoni Ltd.
  • General Contractor (Finishing) -Advance Construction & Dev’t Ltd.
  • Sub-Contractor-Electrical -Sulana Electricals Ltd.
  • Sub-Contractor-Plumbing -Prisca Plumbing Services Ltd.
  • Sub-Contractor-Air conditioning -Delta Air conditioners
  • Sub-Contractor-Curtains Wall -IDE Aluminium Systems Ltd.
  • Supplies- Electrical Control – Alta Electricals- Custom Brand
  • Sub -Contractor- Firefighting- Yotek Enterprise
  • Suppliers-Lighting -F. Malawi Engineering Ltd-Philips Brand
  • Suppliers-Power -Tricord Ltd-MEM Brand
  • Suppliers-Lifts -CFAO- Otis Brand
  • Suppliers-Genset -Mantract-caterpiller Brand
  • Suppliers-Cables -Nexus Cable Metal & Agenda Ltd.
  • Suppliers-Electrical Control -Altra Electricals-Custom Brand

First building to be completed and occupied at the Airport City. Tallest panoramic lifts in Accra with magnificent view